Uploaded by kir-05

Quick Guide to Contract Management Sakhalin Energy

advertisement
Contracting & Procurement Principles
*JC Notifications & Thresholds
■ All C&P policies, procedures and working practices are to be consistent with the Company General Business Principles
■ The highest standards of confidentiality and business ethics should be exercised at all phases of Category Management &
Contracting Process (CMCP)
■ Red flags should be identified and reviewed in accordance with Anti-Bribery and Corruption Procedure
■ Ensure compliance with the Company's HSES Policy and HSES Management of Contract Procedure at all phases of CMCP
process
■ Assign HSES banding for Mode 2 HSE critical contracts
■ All Contract Holders are required to complete Contract Holder training and HSES Management of Contracts training
■ All contracts with Government Intermediaries should be reviewed by the Executive Tender Board
■ This guideline applies to all new contracts, its use is also recommended for contract extensions
JC notification requirements – Type (advance time required)
Note: The time counts from the day of JCN actual issue.
Value of contract
Sole Source Strategy
Competitive Tender
Strategy
Environmental /
Scientific works
Applicable Contract
In-Russia works
< 100K
SSSN (15 days)
AWN (1 day)
100K–250K
SSSN (15 days)
AWN (1 day)
SSSN (15 days)
AWN (1 day)
Out-Russia works
Low value
250K–1000K
FCTN (15 days)
BLN (1 day)
AWN (5 days)
SSSN (15 days)
AWN (5 days)
SSSN (15 days)
AWN (5 days)
SSSN (15 days)
AWN (5 days)
Low value
1000K–5000K
FCTN (15 days)
BLN (1 day)
AWN (5 days)
SSSN (15 days)
AWN (5 days)
SSSN (15 days)
AWN (5 days)
SSSN (15 days)
AWN (5 days)
High value
= or > 5000K
FCTN (15 days) +
Advert (14 days)
BLN (1 day)
AWN (5 days)
SSSN (15 days)
AWN (10 days)
SSSN (15 days)
AWN (10 days)
SSSN (15 days)
AWN (10 days)
High value
FCTN – Forthcoming Tender Notification
BLN – Bid List Notification
The BIG Rules
Low value
■ Plan the work; work the plan
■ Do not start work without a signed contract or insurance
■ Obtain approval of negotiation Plan BEFORE you negotiate
■ Do not negotiate on your own – include CP (this includes phone calls)
■ Put instructions in writing
■ Keep records
■ Minute all meetings
■ Know your contract – read it
■ If in doubt – ask
■ Under no circumstances the CH or CE is allowed to solicit bids or quotes from potential contractors
AWN – Award Notification
SSSN – Single Source Strategy Notification
TB Limits
■ MTB: > $1mln sole source; > $10 mln competitive bid; > $1 mln commercial issues
■ MiTB: > $250K and <$1 mln sole source;
> $1 mln and < $10 mln competitive bid;
> $500K and < $5 mln commercial issues
■ ETB: sensitive commercial issues/contracts with government entities & intermediaries
Legend
ACV
BI
Authorised Contract Value
Business Improvement
BoD
Board of Directors
MoA
Contract Engineer
PoA
CE
CED
Committee of Executive Directors
HSES
L
RC
Manual of Authorities
Contract Owner (Budget Holder)
SvB
Supervisory Board
CH
Contract Holder
STB
Secretary of Tender Board
CP
JC
GCM
Contracting and Procurement team
Finance in Business Team
Joint Committee
Global Category Manager
TB
FinOps
TX
SCM
In
to Contract Management
Power of Attorney
Russian Content team
CO
FinB
Quick Guide
Health, Safety, Environment & Security
Legal
Activity
Action
Inform
Tool/Template
Create and maintain key contract records
CE
CH
OmniCom, SAP
Create and maintain pre-contract correspondence records
CE
CH
Create and maintain post-contract correspondence records
CE
CH
Tender Board
Finance Operations
Tax
Supply Chain Manager
Insurance
Please send comments, questions or suggestion to
SEIC-SCM-Business-Improvements@sakhalinenergy.ru
Yuzhno-Sakhalinsk
2011
OmniCom, SAP
Pre-Award
Establish Scope, Spend, Risks & Complexity
Appoint Contract Holder
Action
Review
CH
Approve
Support
Inform
CO
CP; FinB
L, Tax, In,
SAP
CO
CP
Assess Need
Prepare Contract Requisition Form
CATEGORY MANAGEMENT & CONTRACTING PROCESS
Market Analysis
CH
CO
CE, HSES,
L, Tax, In
CE
CH Appointment Letter; CH Change Form; CH Handover Form
Contract Requisition
Form (CRF)
Understand industry marketplace, suppliers, other industry solutions to gain a competitive advantage
CE
CH, RC/BI
Provide market analysis information and identify levers in the supply market
CE, CH
CP, GCM
Determine & assess current & potential suppliers that could meet the business objectives and scope
delivery
CE, CH
RC, GCM
CE
CH, CP
BI
Board Contract and Variation Approval Procedure Template ( Attachment 2)
CH, CE
CP, FinB
GCM
TCO Model (when applicable)
Develop cost analysis and cost model
CH, CE
CP; HSES
Risk Assessment Matrix (RAM); and Risk Register (when required)
List of potential
suppliers
Identified Cost Drivers
and Value Levers
in TCO, company
estimate
CP, FinB
Contracts
Segmentation
Gold> $20M<Silver
>$5M<Bronze>$250K
G, S, B
Contract Requisition Form (CRF)
CH
Initiate and be actively involved in Total Cost of Ownership model development and seek
improvement opportunities
CO
CP; FinB;
HSES
Tool/Template
Prepare assessment of HSE and other risks (not required for Mode 3)
Invitation to shareholders to nominate a max of 2 potential tenderers (>$15 mln)
Supply Chain Cost
Modeling
Outcome
When applicable
G - RAM mandatory
S, B - RAM
recommended
G - mandatory
S, B - as required
by SCM
Software Template
Basic Should Cost Model/Price Discipline Model
Software Template
G,S
G - mandatory
S, B - as required
by SCM
Key Cost and Value Drivers
Strategy Selection
Develop Contract Strategy
CH, CE
CP, GCM
Formulate strategies to ensure delivery of Goods & Services and value creation
CH, CP
GCM
TBS preparation for TB Strategy approval
CH, CE
MoA; or
require TB
JC* (see JC
CP, FInB
Develop Sourcing Tactics
CH, CP
Select contract form, reward & performance tracking mechanisms (where applicable)
CH, CP
Confirm Suppliers
CH, CP
Undertaking of the pre-qualification of suppliers for inclusion in the list of tenderers
CH, CP
CO
TBS preparation for bidders list approval
CH
CO
Preparation of the Technical evaluation criteria and model
CH
CP, GCM
Preparation of the Commercial evaluation criteria and model
CP
CH, GCM
Develop Invitation to Tender (ITT) including Scope of Work
Issue Invitation to Tender (ITT)
Receive Tender
Sourcing & Award
CO
CH/CP
notifications
box)
GCM; CP
Contract & Sourcing
Strategy (KPIs,
incentives/penalties)
RC
MoA; or
require TB
CP
Pre-qualification Guideline
ITT Template
CH
STB, BI
CP
CO, CH
Draft HSES Management Plan (if applicable)
CH
TBS preparation for contract award approval
CH, CE
HSES
CO
CE, CH
MoA; or
require TB
CP
BoD
Contract Template
Technical &
Commercial evaluation
models
CP
Conduct Commercial Evaluation only after Technical endorsed
JC*
BI
Sign contract
SvB
CP
CH; FInB;
CP
SCM/ PoA
CP; HSES;
L; TX
CP
Dedicated mailbox
G, S, B
(competitive only)
Contract
HSES Management
Plan
HSES Management Plan Template
G, S, B
(HSE-critical)
Recommendation for
contract award
Tender Board Submission Form
G, S, B
Some exceptions may apply, see Cl.3.6 of CPPM (BOD resolution is
required for all contracts with shareholders and their affiliates)
G
Cl. 3.7 of CPPM
G, S
(single source only)
Approved award
Signed contract
CH, CE
G, S, B
(competitive only)
G, S - mandatory
B - discretionary
(competitive only)
HSES; L;
TX
CP
CO, CP
Complete the Final Approval Round Sheet (ARS)
G, S, B
G, S - required
B - optional
JC*
G, S, B
CE hold the contract file
Initiate Start–up
Ensure Contract
management
compliance
& contract
performance
improvements
Close Out &
Feedback
Conduct internal & external kick-off meetings to ensure alignment of supplier with company
requirements for Goods & Services and identify risk and opportunities in delivery
Action
Review
Approve
CH, CP
Support
Inform
CP
HSES
Finalize Contract Management Plan where ACV > $5 mln
CH
CO
CP; FinB;
HSES;
Maintain post award Contract Management Plan where ACV > 5 mln and HSES Management Plan for
HSE critical contracts
CH
CO
Conduct Business Performance Reviews (BPRs), where ACV > 5 mln, HSE Critical Mode 1 & 2
CH
Monitor financial controls: commitments to date; values of work done, invoices received,
commitments against the ACV and expenditure forecasting
Outcome
Contract Mgt Plan
(ACV>5Mln)
Tool/Template
Contracts
Segmentation
Gold> $20M<Silver
>$5M<Bronze>$250K
G, S, B
Contract Management Plan Template
G, S
CP; HSES;
FinB
Contract Management Plan Template
G, S
CO
CP; HSES;
FinB
Business Performance Review (BPR) Guideline
G, S
CH
CO
CP, FinB,
FinOps
Contract Summary Report and Contract Spend by Consuming
departmental Budget Report delivered by FinOps
G, S, B
Identify and secure all required approvals for any new commitments in the scope of work and ACV
increase, extension of contract, change of commercial terms, claims / disputes and / or suspension /
termination of contracts (with ACV >US$100K) by consulting CPPM and associated documents.
CE
CH
Cl. 3.11 of CPPM sets forth the list of cases in which a Tender Board
approval shall be sought. In certain cases CED, BoD and / or SvB approval
might be required (ref. Cl. 3.6, 3.7, 3.8)/Tender Board Submission Form
G, S, B
Raise necessary SAP documents such as Purchase Requisition (PR) and Service Entries (SE). Fully
responsible for SE release
CH
FinOps, CP
G, S, B
Retain ownership of Company supplied goods and ensure the supplier understands his responsibility
for care custody and use of the Goods
CH
FinOps
G, S, B
Manage Claims & Disputes
CH
CO
TB
CP;FinB; L
G, S, B
Manage Suspension &Termination
CH
CO
TB where
ACV>
100K; L
CP
G, S, B
Secure completion and delivery of Goods/Services
CH
CO
CP
G, S, B
Execute and document close-out
CP
TB, CED,
BoD, SvB
CO, FinB
SCM; L; TX;
JC*
CH
Contract close-out
Contract Close-out and final release Certificate
Contract Close out letter
G, S, B
Contract Performance Feedback report
Short list of bidders
RC, HSES
CO
CH
Prepare information for SvB approval (>$15 mln sole source)
Tender Board Submission Form
Long list of bidders
Conduct Technical Evaluation
Prepare request for BOD resolution for contract award
Strategy workshop (when applicable)
Activity
CATEGORY MANAGEMENT & CONTRACTING PROCESS
Activity
Post-Award
Evaluate and record supplier & company performance
CH
CO
RC; CP
G
Opportunities & Lessons Learned
Download